Wednesday, July 20, 2011

Progress!

I feel like writing that in shouty all caps, and the hugest font I can find, but I'm going to spare you that.

What I'm not going to spare you are the details!

The mystery of the plumber was solved: he didn't come Monday because the delivery of the radiators which was scheduled for today had been rearranged for yesterday. That did happen, so when we got home from shopping there are piles of radiators/towel rail/shower screens and other miscellaneous stuff dotted about the bedroom. He's coming on Thursday to fit the towel rail, then take it off again so that M. Waeber can tile behind it.

He'll then re-fit it some time next week when M. Waeber has finished.

Unfortunately, the plasterboarding is leaving something to be desired: the base of the niche is too low, but M. Waeber has made that up with a chunk of Ciporex, but it's the wonkiness of the walls that is causing him the greatest headache.

He's having to use extra tile cement to level out the walls.

Obviously we never realised that the way SMS had stored the plasterboard would cause problems, but it is doing. We said to M. Waeber that next time we would get M. Roncari to do it, but apparently he's ditched the plastering side of the business and only does painting and decorating now. Apparently, there is a good chap in the Haute Marne, so I must remember to ask for his details for my book.

It's lovely to see tiles going up [and hear the thump of tiles being manoeuvred into place, although David is fearful when he sees them being whacked with a mallet!], and the fact that the plumbing/heating supplies are nearly all here makes me very hopeful that it will be finished within a couple of weeks.

Apart from my bit [cleaning & rearranging furniture, belongings etc], of course!