Thursday, April 21, 2011

Thursday, 11.20

Messrs Hamid and Jamel have gone; they finished the joints on the plasterboard that Hamid had replaced/installed yesterday, and that's the builder & plaquiste "lots" finished.

The joiners are all still hard at work fitting shutters and internal doors.

I had a message from the electrician who is stuck on a job at Belfort (195 miles away), so he can't come until next week, but (says he) will call Tuesday to let me know whether he's expected Tuesday or Wednesday.

No news from the plumber, but it's not late yet given that we've still got all afternoon.

Just had a call from M. Mekki, checking that everything's OK, which it is, so all I had to do was thank him for sending Hamid and Jamel and wish him a Happy Easter. Hopefully he will come and look at the work for himself next week, so we can say a proper 'thank you' for all his hard work and willingness to fit in around our difficult schedule.